QuestionQ369

Tools and Documentation

Which of the following is most likely to occur when a team reviews the backlog and reports the status of each task?

  • A Sprint retrospective
  • B Sprint review
  • C Sprint planning
  • D Daily Scrum
Explanation

The Daily Scrum is used to inspect progress toward the Sprint Goal and adapt the Sprint Backlog. Team members communicate progress and current work status so they can plan the next day’s work.