QuestionQ346

Project Management Concepts

During a quality analysis review, the causes of several issues have been identified. Which of the following should the project manager use to determine the MOST important causes?

  • A Ishikawa diagram
  • B Scatter diagram
  • C Pareto chart
  • D Decision tree
Explanation

A Pareto chart orders causes by their frequency or impact, helping identify the vital few that account for the largest share of problems.