Given the following Pareto chart showing defect frequency:

Question Image

Which action should the project manager prioritize to address the defects?

  • A Address fittings and installation defects first.
  • B Address electrical and software defects first, then fittings defects.
  • C Address fittings defects first.
  • D Address hardware and installation defects first, then software defects.
Explanation

Pareto analysis prioritizes the defect category with the greatest frequency because correcting it yields the largest immediate reduction in total defects. Fittings defects are the most frequent category.