QuestionQ317

Project Management Concepts

A highly rated negative risk activates a risk trigger, but the issue has not yet begun. What should the project team do next?

  • A Execute the contingency plan.
  • B Perform a work-around.
  • C Escalate to senior management.
  • D Assign a risk owner.
Explanation

A risk trigger is a predefined condition indicating that the planned contingency response should be activated. A workaround is developed when an unforeseen issue has already occurred, whereas risk ownership is assigned during risk planning.