QuestionQ314

Project Management Concepts

A project manager is applying an agile methodology to lead the implementation of several features that are expected to be developed concurrently. Which of the following should the project manager consider a concern?

  • A Each feature will have a different owner.
  • B The majority of the team can only meet on a weekly basis.
  • C The stakeholders have provided a specific deadline to meet.
  • D Each feature has a specific budget allocation.
Explanation

Agile delivery relies on frequent collaboration and feedback to coordinate work, expose dependencies, and resolve impediments quickly. Limiting most of the team to weekly meetings weakens that cadence and creates a material risk for concurrently developed features.