QuestionQ312

Tools and Documentation

During a team meeting, two developers state plans to work on the same feature. Which of the following should the project manager use to clarify each person’s action items?

  • A Project charter document
  • B Records management plan
  • C Success criteria guide
  • D Responsibility assignment matrix
Explanation

A responsibility assignment matrix maps project work or deliverables to the individuals responsible for them, making ownership of each action item clear and preventing duplicated effort.