QuestionQ310

Tools and Documentation

What can a project manager conclude from the following velocity chart?

Question Image

  • A The project is on schedule.
  • B The project is ahead of schedule.
  • C The project is behind schedule.
  • D The project is at risk.
Explanation

Actual remaining effort is below the planned remaining-effort line at the latest point shown, indicating that work is being completed faster than planned and the project is ahead of schedule.