A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the BEST tool to track this data?
AGantt chart
BProject organization chart
CProgram Evaluation Review Technique chart
DMilestone chart