During the planning phase, a project manager decides to introduce a new enterprise portal tool that the PMO has approved. What should the project manager do next?

  • A Create a transition plan.
  • B Add training to the schedule.
  • C Update the project charter
  • D Involve the CCB.
Explanation

Since the new portal tool is already PMO-approved, no additional CCB involvement or charter revision is required. The logical next step during planning is to add training for the new tool to the project schedule, ensuring team members are prepared before the tool is deployed. This scheduling of training activities is more immediate than transition planning and directly supports adoption.