Project A and Project B have a team member in common. The team member is behind schedule on a task for Project B. Which of the following is the BEST action to take to bring the Project B task back on track?

  • A Negotiate to get more of the team member's available time.
  • B Assign the team member to work overtime to finish the task.
  • C Speed up completion of the task by assisting the team member.
  • D Have the project manager complete the task.
Explanation

When a resource is shared across projects, schedule recovery should be addressed by negotiating sufficient resource availability. This resolves the capacity constraint while maintaining appropriate responsibility for the assigned work.