QuestionQ26

Tools and Documentation

During testing, testers identify multiple bugs that could endanger the project commitment date. Which tool should the project manager use first to update these findings?

  • A Defect log
  • B Change log
  • C Issue log
  • D Risk log
Explanation

A defect log records, tracks, and manages defects discovered during testing, including the information needed for their resolution and status monitoring. Multiple identified bugs should therefore be documented there first.