QuestionQ250
Project Management ConceptsA project manager has been scheduling and facilitating project meetings, recording and distributing the minutes, and sending agendas before upcoming meetings. However, the project manager is frustrated because action items are not being completed. What should the project manager do to address these concerns?
- A Use a software tool during the meeting that can create a transcript of what is discussed.
- B Have a standing agenda that is vague enough so that it can be used again.
- C Delegate the roles and responsibilities to improve meeting management.
- D Reprimand project team members for not completing assigned action items.