QuestionQ244

Tools and Documentation

Which artifact should project team members use to determine whom to communicate with and at what level?

  • A Concept of operations
  • B WBS
  • C Integrated master schedule
  • D RACI
Explanation

A RACI matrix defines each stakeholder’s communication and participation role as Responsible, Accountable, Consulted, or Informed. It therefore identifies the appropriate people and their required level of involvement.