QuestionQ225
Tools and DocumentationWhile implementing code, a senior developer and junior tester discuss the testing scenarios that were completed. A major malfunction caused the product to become inoperative. Consequently, the team had to work until midnight to restore operations. Which of the following should the PM have created FIRST to reduce this issue’s impact before deployment?
- A A risk budget
- B A risk impact
- C A change request
- D A contingency plan
Community Discussion