QuestionQ189

Project Management Concepts

A project manager is preparing a project charter and has successfully documented the project objectives and success criteria. Which of the following should the project manager define next to complete the project charter?

  • A Proposed solution design
  • B Preliminary scope statement
  • C Responsibility assignment matrix
  • D Initial budget baseline
Explanation

A project charter establishes the project at a high level, including its objectives, success criteria, and preliminary scope. The preliminary scope statement defines the project’s initial boundaries and high-level work, while solution design, responsibility assignments, and a budget baseline are planning artifacts developed in greater detail later.