QuestionQ182
Project Management ConceptsA project manager receives an escalation from an external group stating that an expected deliverable should have been available earlier. After analysis, the project team determines that the deliverable was provided on time. What should the project manager do NEXT?
- A Request a change control ticket.
- B Review the schedule plan.
- C Refine the project documentation.
- D Revise the communication plan.