QuestionQ165
Project Management ConceptsA project manager reports that implementation of a new system is on track for completion under budget and ahead of schedule. A stakeholder then asks the manager to add mobile-device functionality. How should the project manager respond to this request?
- A Decline because it is not included in the project scope.
- B Assess the impact of the request and create a change request.
- C Create new functional and non-functional requirements for mobile devices.
- D Revise the baseline of the project plan by adding the new requirements.
Community Discussion