A project manager reports that implementation of a new system is on track for completion under budget and ahead of schedule. A stakeholder then asks the manager to add mobile-device functionality. How should the project manager respond to this request?

  • A Decline because it is not included in the project scope.
  • B Assess the impact of the request and create a change request.
  • C Create new functional and non-functional requirements for mobile devices.
  • D Revise the baseline of the project plan by adding the new requirements.
Explanation

Mobile-device functionality adds or changes project scope, so it must be assessed and processed as a formal change request. The project baseline and detailed requirements are updated only after the change has been evaluated and approved through change control.