QuestionQ135
Project Management ConceptsDuring project execution, a project manager discovers that the project sponsor will change. What is the first action the project manager should take?
- A Mitigate risk.
- B Develop a contingency plan.
- C Add the change to the risk register.
- D Execute an impact analysis.