QuestionQ118

Project Life Cycle Phases

Project stakeholders have requested that the team use Scrum to manage a software implementation project. Which of the following would be most likely to occur during a Scrum ceremony?

  • A Reviewing project blockers
  • B Defining roles and responsibilities
  • C Establishing a project schedule
  • D Determining a project budget
Explanation

Scrum events provide regular opportunities for the team to inspect progress, coordinate work, and identify impediments. Reviewing project blockers supports removing obstacles that could prevent the team from meeting its Sprint Goal.