QuestionQ111
Project Management ConceptsA developer concentrated on one story for an entire Sprint. The story was underestimated and therefore was not completed. Which of the following actions should the Scrum Team take NEXT?
- A Assign more resources to complete similar stories in the future.
- B Break the stories into workable items that can be completed within one sprint.
- C Extend the sprint duration when required with the approval of the product owner.
- D Release the current progress into production and carry over the rest of the code for the next sprint.