QuestionQ108

Project Life Cycle Phases

In a functional organization, a project has been completed successfully. Which of the following actions would the project manager be MOST likely to take?

  • A Assemble a new project with existing resources.
  • B Obtain the final report from release management.
  • C Notify the functional manager that resources are released.
  • D Allocate resources in a different project.
Explanation

In a functional organization, functional managers control staff and resource assignments. Once the project is complete, the project manager notifies the functional manager that the project’s resources are released for reassignment.