QuestionQ41

Deployment

A development team is prepared to release the newest version of an application. Which of the following strategies best ensures a successful deployment without affecting the bandwidth of company resources?

Explanation

Blue-green deployment runs the new release in a separate, production-capable environment and redirects traffic only after validation. This enables a controlled cutover and rapid rollback while avoiding the duplicated live-request traffic characteristic of shadow deployment. Microsoft describes blue-green deployment as using two separate environments and allowing rollback to the stable environment if problems or performance degradation occur.