An analyst needs to perform a risk assessment for a newly deployed application. Given the following information:

  • The total budget allocation for the new application is unavailable.
  • Recovery time objectives have not been established.
  • Downtime-loss calculations cannot be supplied.

Which statement explains why a qualitative assessment is the best option?

Explanation

Qualitative risk assessment is used when sufficient reliable metrics are unavailable for a quantitative analysis. Missing budget information, recovery time objectives, and downtime-loss calculations prevent calculating monetary or other numerical risk values.