QuestionQ36

Integrations

A Cisco ACI fabric must integrate with a VMware vSphere environment. One ESXi host remains disconnected from the Distributed Virtual Switch (DVS) and the VMM domain. Two EPGs have already been created and linked to the VMM domain. An engineer must prepare the ACI configuration so that:

  • EPG contracts are sent to ACI leaf switches before a hypervisor attaches to the DVS.
  • EPG contracts are pushed to leaf hardware immediately when the policy is downloaded to the leaf software.

Which EPG configuration must be used to satisfy these requirements?

Explanation

Pre-provision resolution immediacy downloads EPG policies, including contracts and filters, to ACI leaf switches even before a VM controller or hypervisor attaches to the VMware Distributed Virtual Switch. Immediate deployment immediacy programs the policy into the leaf hardware policy CAM as soon as it is downloaded into leaf software.