Refer to the exhibit. A client configures an upgrade for Cisco Nexus switches connected to the Cisco ACI controller so that the switches are upgraded one at a time. After the upgrade runs, both Cisco Nexus switches are found to have upgraded simultaneously. Which two actions ensure that the switches upgrade one at a time?

Choose two
Explanation

Graceful Maintenance enables the graceful switch-upgrade process. APIC-connected leaf switches must be placed in separate maintenance/upgrade groups so that one remains operational while the other upgrades, preserving APIC connectivity and preventing simultaneous upgrade. Cisco documents this redundancy requirement for graceful ACI switch upgrades.