An engineer is troubleshooting a fabric-discovery failure. Which two switch-connectivity requirements must be verified to resolve the issue?

Choose two
Explanation

Cisco ACI discovery begins with an APIC directly connected to a leaf switch. Once that leaf is registered, the APIC discovers the spine switches connected to it, then the leaf switches connected to those spines. The ACI leaf-spine fabric topology uses APIC-to-leaf connections and leaf-to-spine fabric links; spine-to-spine and APIC-to-spine connections are not part of this topology.