QuestionQ94

Administrative and Operational Tasks

A host in the cluster has a permanent NIC failure, and the replacement component will not arrive until the following morning. The administrator must ensure that the production workload remains available at all times.

Which action should the administrator take to achieve this goal?

  • A Disable the vSAN Service on the VMkernel port
  • B Perform a live vMotion to another host
  • C Enter Maintenance Mode with "Full Data Migration"
  • D Shut down the production VMs
Explanation

Live vMotion relocates powered-on virtual machines to another host while they continue running, preserving production workload availability despite the affected host’s NIC failure.