QuestionQ69

VerifiedIntake and planning

Company A’s executive team asks the Workfront System Administrator how they can gain visibility into the health, importance, and strategic alignment of active projects throughout the organization so they can make data-driven business decisions quickly.

Which report provides this visibility?

Explanation

Project Condition is a reportable indicator of how a project is progressing, and the Project Priority field is a manually assigned flag that communicates a project’s importance and is used primarily for reporting. A project report filtered to active projects, grouped by portfolio, can present both fields along with custom project data that maps each initiative to business goals.

Learn more