QuestionQ44
VerifiedIntake and planningThe final 5 tasks in a project must occur within 10 days of the project's end.
Which Task Constraint should the project manager use to configure this timeline without specifying exact dates?
The final 5 tasks in a project must occur within 10 days of the project's end.
Which Task Constraint should the project manager use to configure this timeline without specifying exact dates?