QuestionQ42

VerifiedExecute

Given the following information about a Task:

  • Planned Start Date: May 14 -
  • Actual Start Date: May 14 -
  • Planned Completion Date: May 20 -
  • Projected Completion Date: May 22
  • Percent Complete: 50%
  • Duration: 5 Days -
  • Planned Hours: 8 Hours -
  • Status: In Progress -

If today were May 19, what would the Task’s progress status be?

Explanation

A task is behind schedule when its projected completion date is later than its planned completion date. This task is projected to finish on May 22 rather than its planned May 20 completion date, and it is only 50% complete on May 19.