QuestionQ39
VerifiedIntake and planningA company has decided that every project for the year must be created from templates and staffed in the following quarter. The projects must stay in a backlog until the team has capacity to work on them. Previously, confusion arose because the team used the Planning status for all work that had not started.
What should the project manager do to help the team distinguish work in the backlog from work that is now being planned?