QuestionQ34

VerifiedIntake and planning

Task 1 in Project 1 can start only after the final milestone in Project2 has been completed.

How should the project manager configure this relationship?

Explanation

A cross-project predecessor is added to the dependent successor task. Assigning the final milestone in Project2 as a predecessor of Task 1 in Project1 creates a finish-to-start dependency, preventing Task 1 from starting until that milestone is complete.