QuestionQ22Verified/Intake and planningCopy linkReport a problemAsk AstroTutorSave questionWhich project components can be used to measure a project’s compliance with its original schedule?ANumber of tasks, actual completion dates, and project statusBProject baselines, planned completion dates, and actual completion datesCWorkload balancer data, planned completion dates, and expensesShow AnswerAnswerExplanationProject baselines retain the original schedule for comparison. Planned completion dates and actual completion dates show whether work completed as originally scheduled and reveal variances from that baseline.Show comments0Show commentsCommunity DiscussionNo comments yet. Be the first to start the discussion!