QuestionQ22

VerifiedIntake and planning

Which project components can be used to measure a project’s compliance with its original schedule?

Explanation

Project baselines retain the original schedule for comparison. Planned completion dates and actual completion dates show whether work completed as originally scheduled and reveal variances from that baseline.