QuestionQ22

Intake and planning

Which project components can be used to measure a project’s compliance with its original schedule?

  • A Number of tasks, actual completion dates, and project status
  • B Project baselines, planned completion dates, and actual completion dates
  • C Workload balancer data, planned completion dates, and expenses
Explanation

Project baselines retain the original schedule for comparison. Planned completion dates and actual completion dates show whether work completed as originally scheduled and reveal variances from that baseline.