QuestionQ15Verified/ExecuteCopy linkReport a problemAsk AstroTutorSave questionWhat happens when an individual enters a new Commit Date that is later than a task’s original Planned Date?AThe assignee of any task that has the original task set as a predecessor is notified.BThe Project Owner is notified whether this change will impact the Project Timeline.CThe Planned Completion Date of the task automatically changes to match the new Commit Date.Show AnswerAnswerExplanationIn Adobe Workfront, changing an assignee’s Commit Date sends a notification to the Project Owner so the proposed date and its potential project-timeline impact can be assessed. The change does not automatically update the task’s Planned Completion Date; the Project Owner can update that date manually if appropriate.Learn moreUpdate Commit Dates on Tasks and IssuesInteractions Between the Commit Date and the Planned Completion DateShow comments0Show commentsCommunity DiscussionNo comments yet. Be the first to start the discussion!