QuestionQ15

Execute

What happens when an individual enters a new Commit Date that is later than a task’s original Planned Date?

  • A The assignee of any task that has the original task set as a predecessor is notified.
  • B The Project Owner is notified whether this change will impact the Project Timeline.
  • C The Planned Completion Date of the task automatically changes to match the new Commit Date.
Explanation

In Adobe Workfront, changing an assignee’s Commit Date sends a notification to the Project Owner so the proposed date and its potential project-timeline impact can be assessed. The change does not automatically update the task’s Planned Completion Date; the Project Owner can update that date manually if appropriate.

Learn more