QuestionQ191
VerifiedUiPath Deployment OptionsConsider the following scenario:
A customer has an on-premises Orchestrator installation and wants to begin a new project using Document Understanding and ML. The project must be deployed to production within 6 weeks, but AI Center and Document Understanding are unavailable because they are not installed.
Also consider the following:
- Any cloud solution requires an approval process of roughly 4 weeks for production use and 2 weeks for development/testing.
- Obtaining hardware resources for an on-premises installation will take roughly 5 weeks, and the costs barely fit the customer’s budget.
- The Orchestrator installation must remain unchanged.
Which deployment option minimizes the risks of getting the process into production on time?