QuestionQ191

VerifiedUiPath Deployment Options

Consider the following scenario:

A customer has an on-premises Orchestrator installation and wants to begin a new project using Document Understanding and ML. The project must be deployed to production within 6 weeks, but AI Center and Document Understanding are unavailable because they are not installed.

Also consider the following:

  • Any cloud solution requires an approval process of roughly 4 weeks for production use and 2 weeks for development/testing.
  • Obtaining hardware resources for an on-premises installation will take roughly 5 weeks, and the costs barely fit the customer’s budget.
  • The Orchestrator installation must remain unchanged.

Which deployment option minimizes the risks of getting the process into production on time?

Explanation

A hybrid deployment retains the existing standalone on-premises Orchestrator while using cloud-hosted AI Center and Document Understanding ML packages. It avoids the approximately five-week hardware-acquisition dependency of an on-premises deployment, does not alter Orchestrator, and its roughly four-week cloud-production approval can complete within the six-week delivery window. UiPath documents this configuration as a Hybrid deployment using a standalone Orchestrator with Automation Cloud AI Center and Document Understanding.