QuestionQ40

VerifiedProcess Analysis

When prioritizing processes from a pipeline, in what sequence should development be completed?

Drag & Drop
1st
2nd
3rd
4th
Explanation

When prioritizing automation processes from a pipeline for development, the standard impact-versus-effort prioritization approach places Quick Wins first because they deliver high business value for minimal implementation effort and build early momentum. Must-Do Improvements come second because, despite requiring more effort, they still deliver high impact and are necessary commitments. Low-Hanging Fruit is addressed third: these are easy, low-effort items but with lower overall impact, so they are picked up once the highest-value work is underway. Long-Term Improvements are scheduled last because they combine higher effort with lower relative impact, making them the least time-sensitive items in the backlog.