QuestionQ37
Risk Implementation ApproachA risk manager is reevaluating a completed risk assessment project to incorporate new insights.
What occurs to risks that were assessed previously during this process?
- A Previously assessed risks are automatically carried over for reassessment
- B All previously assessed risks are deleted and must be reassessed from scratch
- C Previously assessed risks are archived and excluded from the reassessment
- D All previously assessed risk assessments are marked as resolved and closed
Community Discussion