QuestionQ244

Risk Implementation Approach

What occurs when a scoped risk is removed from a ServiceNow risk assessment project?

  • A The risk is marked as not applicable and remains part of the project.
  • B The risk is moved to a separate list for future reassessment.
  • C The risk is removed from the risk assessment project.
  • D The risk is archived and can be restored at any time.
Explanation

A removed scoped risk remains in the risk assessment project and is marked as not applicable for reporting purposes. ServiceNow treats ad hoc risks differently: removed ad hoc risks are completely deleted.