QuestionQ171

Audit Management Implementation

Which baseline criteria govern when notifications are triggered for audit tasks?

Choose two
  • A Expiration
  • B At 50% completion
  • C Reassignment
  • D Due date change
Explanation

Baseline audit-task notifications are triggered when a task expires and when it is reassigned, ensuring that overdue work is escalated and a new assignee is informed. Reaching 50% completion and changing a due date are not baseline notification triggers.