QuestionQ8

PI Planning Preparation

Which statement characterizes a mitigated ART PI Risk?

  • A There is a strategy to adjust the plan as necessary
  • B Nothing more can be done, so if a risk occurs, release may be compromised
  • C Someone has taken the responsibility of the risk
  • D The risk has been addressed and is no longer a concern
Explanation

In SAFe’s ROAM risk approach, a mitigated risk has a strategy for adjusting the plan as necessary if the risk materializes.