QuestionQ36

Iteration Execution

What is one way to establish a team’s velocity?

  • A Add the Story points for all the Stories planned for the Iteration
  • B Compare the average Story points completed throughout the previous Iterations
  • C Add the Story points for all Features completed in the Iteration
  • D Calculate the percentage planned versus actual Stories completed during an Iteration
Explanation

A team’s velocity is established from its historical delivery rate: the average story points completed over previous iterations. This measures completed work and provides a reliable basis for future iteration planning.

Learn more