QuestionQ36Verified/Iteration ExecutionCopy linkReport a problemAsk AstroTutorSave questionWhat is one way to establish a team’s velocity?AAdd the Story points for all the Stories planned for the IterationBCompare the average Story points completed throughout the previous IterationsCAdd the Story points for all Features completed in the IterationDCalculate the percentage planned versus actual Stories completed during an IterationShow AnswerAnswerExplanationA team’s velocity is established from its historical delivery rate: the average story points completed over previous iterations. This measures completed work and provides a reliable basis for future iteration planning.Learn moreSAFe Extended Guidance: Iteration PlanningShow comments0Show commentsCommunity DiscussionNo comments yet. Be the first to start the discussion!