QuestionQ31

PI Execution

What is one approach to managing complex critical-path challenges?

  • A Distribute work to other teams
  • B Sequence work to eliminate same Iteration dependencies
  • C Adjust work between teams or split Features and Stories
  • D Allocate work between teams based on forecasted capacity
Explanation

Complex critical paths are mitigated by restructuring the work to reduce blocking dependencies, such as moving work between teams or splitting Features and Stories into smaller, more independently deliverable pieces.