QuestionQ27Verified/PI Planning PreparationCopy linkReport a problemAsk AstroTutorSave questionWhat is one activity involved in determining a team’s initial capacity during PI Planning?ACompare final team capacity across all teamsBAdd together all of the points from recently completed FeaturesCSubtract one point for every team member’s vacation day, public holiday, or training dayDEnsure Product Owner/Product Manager approval for all time-based capacity adjustmentsShow AnswerAnswerExplanationInitial team capacity must be adjusted for time when team members are unavailable. Deducting capacity for vacation days, public holidays, and training days produces a realistic estimate of the team’s available time for the PI.Show comments0Show commentsCommunity DiscussionNo comments yet. Be the first to start the discussion!