QuestionQ62

Governance

Universal Containers has established a software tool to support agile processes, but the development team does not update the status of its work in progress regularly.

Which Scrum value is undermined by this poor practice, and why?

  • A Focus, because the teams are not focusing in the agile process expected activities.
  • B Courage, because the teams should be transparent about progress and speak up when they need help.
  • C Commitment, because the team is not committed to following the Agile methodology.
Explanation

Courage requires Scrum Team members to do the right thing and address difficult problems. Accurately sharing work status and speaking up when help is needed enables the transparency required for inspection, adaptation, and timely removal of impediments.