QuestionQ24

VerifiedRisk Identification and Mitigation

Universal Containers (UC) is partway through a large enterprise project. UC is using an agile model and currently has four-week iterations, supported by a branching strategy that fits this approach. UC operates in a strict regulatory environment and has dedicated security, QA, and release-management teams. The system is live for users, and a serious production issue is found at the beginning of a sprint and traced to a bug in Apex code.

Which three approaches should an architect recommend to resolve this bug?

Choose three
Explanation

A production defect requires an expedited, governed hotfix rather than a direct production edit or waiting for the ordinary release. A dedicated hotfix branch isolates the emergency correction from ongoing sprint work; assessing possible data effects protects the live system and supports remediation planning; and stakeholder approval ensures the accelerated deployment still follows the organization’s regulatory change-control and release-management requirements. Salesforce guidance recommends developing outside production and evaluating user impact before production deployment.

Learn more

Community Discussion

No comments yet. Be the first to start the discussion!