QuestionQ96

Delivery

An agile team and a traditional development team are collaborating on a project. Although each team exceeds expectations for its deliverables, problems occur when those deliverables are integrated.

What should the agile practitioner do?

  • A Foster stronger communication by hosting cross-organizational meetings between the two teams
  • B Suggest merging the teams to avoid misunderstandings
  • C Create stories from full technical specifications to avoid ambiguity
  • D Co-locate the teams to encourage osmotic communication
Explanation

Integration problems between independently successful teams usually arise from insufficient coordination, unclear dependencies, or mismatched expectations. Regular cross-organizational communication creates a shared forum to surface and resolve those issues while preserving each team’s working approach.