QuestionQ68
ProductAt the conclusion of a product development phase, an agile project team verifies that every test has passed. The product is released, yet the customer complains that it is deficient.
What should the project team have done before releasing the product?
- A Requested approval from the project sponsor
- B Undertaken a review of all requirements
- C Conducted an end-of-phase demonstration
- D Performed a retrospective to validate project deliverables