QuestionQ68

Product

At the conclusion of a product development phase, an agile project team verifies that every test has passed. The product is released, yet the customer complains that it is deficient.

What should the project team have done before releasing the product?

  • A Requested approval from the project sponsor
  • B Undertaken a review of all requirements
  • C Conducted an end-of-phase demonstration
  • D Performed a retrospective to validate project deliverables
Explanation

An end-of-phase demonstration lets customers and stakeholders inspect the working product and provide feedback before release. This validates that the delivered functionality meets customer expectations, not merely that it passes technical tests.