QuestionQ53

Delivery

A project team identifies several technical challenges with features planned for the next sprint.

What should they do?

  • A Request direction from the technical manager
  • B Encourage that product owner to reallocate the features to another sprint
  • C Determine who is best qualified to address the challenges
  • D Ask the product owner to assign the tasks to the most appropriately skilled resources
Explanation

A self-managing Agile team should use its collective expertise to identify the team member best qualified to address each technical challenge. The product owner prioritizes work rather than assigning tasks or resources, and a technical manager does not direct the team’s day-to-day task allocation.