QuestionQ493
DeliveryA weather-report web page is scheduled to go online next quarter. During the retrospective, discrepancies were found between the customer’s requests and the user experience (UX). The product owner and the development team disagree about what might have gone wrong and caused this.
What should the Extreme Programming (XP) coach do to keep the project on track and ensure it is delivered on time?
- A Release this version and leave changes to be done at the end of the project phase.
- B Arrange a workshop where all ideas will be discussed and take corrective actions ensuring value delivery.
- C Ask the development team to brainstorm and come up with suggestions that will improve the delivery date.
- D Run a spike, identify what went wrong during implementation and request a change to enhance value delivery.