An agile lead is in a project follow-up meeting with a project sponsor. The sponsor requests an estimated project-completion date.

Which two tools should the agile lead use to provide this information?

  • A The current backlog including new stories recently added by the product owner.
  • B The updated project management plan considering delays recently reported by the team.
  • C The list of all risks not yet mitigated, which could affect project execution.
  • D The average velocity and burndown chart with including the points burned in the previous sprints.
  • E The list of impediments reported by the team in daily meetings and not yet resolved.
Explanation

Average velocity uses the team's historical rate of completed work, and a burndown chart shows remaining work and its trend over time. Using both enables a forecast of when the remaining scope is likely to be completed.