QuestionQ491
DeliveryAn agile lead is in a project follow-up meeting with a project sponsor. The sponsor requests an estimated project-completion date.
Which two tools should the agile lead use to provide this information?
- A The current backlog including new stories recently added by the product owner.
- B The updated project management plan considering delays recently reported by the team.
- C The list of all risks not yet mitigated, which could affect project execution.
- D The average velocity and burndown chart with including the points burned in the previous sprints.
- E The list of impediments reported by the team in daily meetings and not yet resolved.